Seemed very fitting for a visit to Knowing Spring Courtyard on the Spring Equinox, and the sun was out too boot.


The shot-crete boys must have worked by moon light: they finished in three days, and today, the carpentry crew commenced with removing the wooden forms. Note the leak window covers are removed, and the general outline of the southern wall has been revealed.



What took weeks to assemble, will come apart much more quickly. But at a pace which will allow adequate strengthening of the concrete before all support is taken away. Here Jack removes a cover from one of the doorways.


              Hmmm, Frank, would OSHA approve of this maneuver?